Project · Airport tenancy fitout

Europcar – Hobart International Airport Fitout

Full car hire tenancy fitout within the new Hobart Airport terminal. CBD Projects delivered joinery, ceilings, services and finishes on a tight program aligned with the terminal opening.

Location Hobart Airport, Tasmania
Completed 2025 · ~2.5 weeks on site
Type Car hire tenancy – new terminal
Completed fitout Airport project
Counters, mural wall and Europcar green feature wall.

Project overview

CBD Projects delivered a full fitout for Europcar within the newly upgraded Hobart International Airport terminal, coordinating closely with airport management, consultants and other contractors on the concourse.

Scope of works

  • Full commercial tenancy fitout within new terminal shell.
  • New counters, custom joinery and back-of-house cabinetry.
  • Slatwall storage units and concealed storage solutions.
  • Metal stud framing, insulation and plasterboard linings.
  • New grid ceilings installed throughout the tenancy.
  • 25 kW engineered and designed ducted air conditioning system.
  • Structured data and communications installed to engineered specifications.
  • Hybrid vinyl plank flooring throughout.
  • Green feature wall with Europcar branding and signage.
  • Coordination with airport electrical, mechanical, fire and data contractors.

Key features & outcome

The fitout balances brand visibility, durability and a clean customer experience, while integrating with the larger terminal environment.

  • Full-height Tasmanian landscape mural as a key visual feature.
  • Integrated cable management within each counter for tidy workstations.
  • Timber slatted feature wall concealing storage and services.
  • Approx. 2.5 weeks on site, aligned with terminal opening dates.
  • Delivered with full compliance documentation and sign-offs.
  • Positive feedback from Europcar with ongoing works nationally for over six years.